一套2x600MW锅炉主要施工组织设计方案(中英文对比)

2022年9月17日暖通工程31
广告也精彩

本期建设规模2×600MW燃煤发电机组。锅炉由SEC提供。锅炉为亚临界参数、强制循环、一次中间再热、单炉膛平衡通风、固态排渣、露天布置、全钢构架的∏型汽包炉。文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

This project is 2×600MW coal fired thermal units, boiler shall be supplied by SEC. The boiler is all steel structural ∏ type drum boiler of a subcritical parameter, pump circulation, single reheat, single furnace balance draft, dry slagging and hypaethral placement.文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

锅炉施工方案  Boiler Erection Plan文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

锅炉为上海电气集团生产的亚临界参数、强制循环、一次中间再热、单炉膛平衡通风、固态排渣、露天布置、全钢构架的∏型汽包炉。文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

The Boiler shall be supplied by SEC. The boiler is all steel structural ∏ type drum boiler of a subcritical parameter, pump circulation, single reheat, single furnace balance draft, dry slagging and hypaethral placement.文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

1 施工场地及主吊机械 Erection site and main hoisting equipments文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

1.1 施工场地布置  Erection site plot

锅炉组合场布置按总平面布置图,组合场内布置50t龙门吊各4台,锅炉受热面的大部分组合工作安排在此完成。文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

Boiler assembly yard will be arranged as per general layout drawing.  Four 50T gantry cranes will be provided respectively. Assembly of most heating surface structures will be done in this area.文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

1.2 施工机械选择 Selection of construction plants

根据本工程锅炉的结构特点,以及我公司的机械状况,选用以下机械作为锅炉主要施工机械。Given to the features of the boier and mechanical capacity of our company, we chose plants below as our main construction equipmemnts.文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

序号Sl机械名称 description机械型号 mode数量quantity
1圆筒吊cylindrical craneFZQ2000/80t2
2履带吊crawler craneCC14001
3龙门吊 frame crane50t4
4履带吊crawler craneCC25001
5劳辛格Stand-jack system200t2
6塔吊 tower craneC7050/20t3
    

(1) FZQ2000/ 80T圆筒吊 FZQ2000/ 80T cylindrical crane文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

FZQ2000圆筒吊做为附吊机械,筒身高度102m,采用60m臂长工况,主要负责锅炉本体部件的吊装工作。FZQ2000 cylindrical crane is arranged as auxiliary hoisting plants, which is designed to hoist boiler & components (crane body height 102m , length of jib 60m).文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

(2)  250t履带吊 250t Crawler crane文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

CC1400/250t履带吊为锅炉主吊机械,采用SWSL塔式工况,后配重40t,主臂角度85度:主副臂:72m加36m;最大作业半径42m,负荷27t;最小作业半径24m时,负荷为39t。文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

CC1400/250 Crawler cranes are designed as main boiler hoisting euqipment, adopting SWSL tower working conditions, with a banlance weight of 40t and main jib angle of 85°; length of main & auxiliary jib,72+36m, max working radius 42m,load 27t;min working radius 24m,load 39t.文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

限于篇幅有限,详细内容请下载参考学习。文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html

资源下载
此资源为免费资源
立即下载
下载说明:
1、本站资源收集于互联网,内容存储于互联网,非VIP会员不保证下载链接时效性。
2、VIP会员(体验、包月、包年、终身)提供稳定下载链接。
3、VIP会员下载遇到问题请联系客服QQ/WX:8-7-7-4-7-6-7-4(去掉-)
文章源自自学土木网-https://www.zxtm.com/fangan/ntgc/3377.html
  • 扫一扫
  • 联系小编加群
  • weinxin
  • 扫一扫
  • 公众号获取大礼包
  • weinxin
广告也精彩
  • 版权说明:
    1、自学土木网为资源共享网站,大部分资源均搜集于互联网免费共享,少数资源可通过VIP会员方式获取权限。
    2、本站资源来自于互联网及网友供稿,仅作为学习研究之用,禁止用于任何商业用途。
    3、如本页侵犯到任何第三方权益,请联系QQ/WX:87747674提交相关证明后我们将及时删除。
    4、百度网盘分享内容难免有被取消情况发生,VIP会员可直接联系上述QQ/WX索取和谐内容。
  • 5、转载请务必保留本文链接:一套2x600MW锅炉主要施工组织设计方案(中英文对比)