扬巴污水提升泵站压密注浆施工组织设计方案

2022年10月5日环保工程4
广告也精彩
  • 前言Preface

污水提升泵站压密注浆主要针对其基坑底板下部的约1.8m厚的粉土,因其底板呈阶梯部,部份土体滑动,造成部份底板与其下部粉土的分离,而形成空洞,目前通过现场勘察,因破坏处为16×3×1.8m。因而要求采用注浆方式进行土体加固。This plan is mainly aimed at about 1.8m THK powder soil in the bottom slab of foundation pit. As the bottom slab is in a step and part of the soil is slided, some slabs are separated from the powder soil. So the hollows turn up. After the site investigation, as the broken area is 16*3*1.8m, method of grouting should be adopted for the soil strengthening.文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html

  • 压密注浆方法Methodology for Compaction and Grouting

该工程基坑底板现已浇注成功,依据现场的破坏程度及以往的施工经验,先通过人工方式在底板开孔,然后依据水灰比0.5~0.6的方案进行搅拌水泥浆,再将搅拌均匀的水泥浆用机械方式输入孔洞中,已达到加固地基土为目的。The bottom slab in foundation pit has been successfully placed. According to the damage degree and our construction experience, firstly we will make hole by manpower, secondly mix cement mortar in a water cement ratio of 0.5~0.6. Then cement mortar will be conveyed into holes by machine to meet the requirement.文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html

  • 施工淮备Construction Preparation
  • 设置制浆站、加浆站尽量减少移动次数。Establish the mortar process station and adding station to minimize the times of removal.
  • 设备调试,检查设备运行的情况。Equipment commissioning. And check the running status for equipments.
  • 备料、搭建水泥存放点。Material preparation. And build the storage for cement.
  • 施工计划Construction Plan
  • 施工设备:水泥浆压力泵一台;泥浆搅拌桶一台;储浆桶一只;注浆杆一根;注浆管50m。Construction Equipments: One cement mortar pressure pump. One bucket for cement mortar mixing. One bucket for storage. One pole for mortar filling and 50m conduit.
  • 人员组织:施工现场在施工项目经理部的领导下,另配压密注浆现场施工负责人1人,熟练压密注浆工6人。Staff Organization: All site staff shall be guided by P.M., with one site construction supervisor and 6 competent and experienced workers for compaction and grouting.
  • 施工技术要求Construction Technical Requirements

1、 技术要求:Technical Requirements文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html

因施工地块现已浇注混凝土底板,固采用风镐进行人工开孔,孔距为2.0m~1.5m,呈梅花形布孔,这样有利于浆液充填。As the site has been placed with concrete, holes will be made by manpower with air pick. These holes will be in a plum blossom shape, with clearance of 2.0m~1.5m to facilitate the full filling.文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html

压浆设备采用200型高压泵注浆,机械动力采用自备柴油机动力,此泵最大压力可达到8MPa。200 type HP pump and self owned diesel generator will be used. The maximum pressure of pump is 8MPa.文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html

资源下载
此资源为免费资源
立即下载
下载说明:
1、本站资源收集于互联网,内容存储于互联网,非VIP会员不保证下载链接时效性。
2、VIP会员(体验、包月、包年、终身)提供稳定下载链接。
3、VIP会员下载遇到问题请联系客服QQ/WX:8-7-7-4-7-6-7-4(去掉-)
文章源自自学土木网-https://www.zxtm.com/fangan/hbgc/4212.html
  • 扫一扫
  • 联系小编加群
  • weinxin
  • 扫一扫
  • 公众号获取大礼包
  • weinxin
广告也精彩
  • 版权说明:
    1、自学土木网为资源共享网站,大部分资源均搜集于互联网免费共享,少数资源可通过VIP会员方式获取权限。
    2、本站资源来自于互联网及网友供稿,仅作为学习研究之用,禁止用于任何商业用途。
    3、如本页侵犯到任何第三方权益,请联系QQ/WX:87747674提交相关证明后我们将及时删除。
    4、百度网盘分享内容难免有被取消情况发生,VIP会员可直接联系上述QQ/WX索取和谐内容。
  • 5、转载请务必保留本文链接:扬巴污水提升泵站压密注浆施工组织设计方案